Policy and Procedure No.: B-26-44
Purpose
This handout establishes a procedure for complete plan review submittals when proposing to install a commercial electric vehicle charging station(s). According to current code regulations and the Elk Grove Municipal Code, permits are required for this type of installation. Therefore, the following guideline shall be reviewed before commencing any work.
Left Content
Submittal Checklist
- A completed building permit application
- A site plan
- An electrical plan
- Equipment Manufacturer’s Installation Instructions
Right Content
Submittal Requirements
- PDF files of forms and plans listed in the submittal checklist
- Submit all PDF forms and plans to the Building Filedrop
Left Content
Plan Requirements
Site Plan
- Building footprints and landscaped areas
- Parking and circulation areas
- Show locations of any existing and all proposed EV stations, panels, and other service equipment
- Demonstrate compliance with accessibility provisions
Right Content
Electrical Plan
- Electrical and equipment layout
- Single line diagram
- Electrical Load Calculations (Existing + New) and Panel schedule
- Demonstrate compliance with accessibility provisions
| Total Number of EVCS At Facility | Minimum Number (by type) Of EVCS Required | ||
|---|---|---|---|
| Van Accessible | Standard Accessible | Ambulatory | |
| 1-4 | 1 | 0 | 0 |
| 5-25 | 1 | 1 | 0 |
| 26-50 | 1 | 1 | 1 |
| 50> | See CBC 2025 Table 11B-228.3.2.1 | ||
Figure 11B-812.9, Surface Marking